CHAPTER 12 REGASIFICATION SYSTEMS
Section 1 General
Section 2 Design of Regasification Systems
3. Systems that contain significant energy are to be depressurised during an emergency situation.
5. During an dimensioning accidental event, the integrity and functionality of depressurising piping and valves is to be maintained for the required period of time in order to ensure that success- ful depressurization can be performed.
3. In case of relief to cargo tanks, the effect of routing high pressure LNG/NG to the cargo tank is to be documented.
Section 3 Regasification System Equipment
< Previous
|
Contents
|